9.8: Key Terms
- Page ID
- 154220
\( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)
\( \newcommand{\dsum}{\displaystyle\sum\limits} \)
\( \newcommand{\dint}{\displaystyle\int\limits} \)
\( \newcommand{\dlim}{\displaystyle\lim\limits} \)
\( \newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\)
( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\)
\( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)
\( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\)
\( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)
\( \newcommand{\Span}{\mathrm{span}}\)
\( \newcommand{\id}{\mathrm{id}}\)
\( \newcommand{\Span}{\mathrm{span}}\)
\( \newcommand{\kernel}{\mathrm{null}\,}\)
\( \newcommand{\range}{\mathrm{range}\,}\)
\( \newcommand{\RealPart}{\mathrm{Re}}\)
\( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)
\( \newcommand{\Argument}{\mathrm{Arg}}\)
\( \newcommand{\norm}[1]{\| #1 \|}\)
\( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)
\( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\AA}{\unicode[.8,0]{x212B}}\)
\( \newcommand{\vectorA}[1]{\vec{#1}} % arrow\)
\( \newcommand{\vectorAt}[1]{\vec{\text{#1}}} % arrow\)
\( \newcommand{\vectorB}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\( \newcommand{\vectorC}[1]{\textbf{#1}} \)
\( \newcommand{\vectorD}[1]{\overrightarrow{#1}} \)
\( \newcommand{\vectorDt}[1]{\overrightarrow{\text{#1}}} \)
\( \newcommand{\vectE}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash{\mathbf {#1}}}} \)
\( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\(\newcommand{\longvect}{\overrightarrow}\)
\( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)
\(\newcommand{\avec}{\mathbf a}\) \(\newcommand{\bvec}{\mathbf b}\) \(\newcommand{\cvec}{\mathbf c}\) \(\newcommand{\dvec}{\mathbf d}\) \(\newcommand{\dtil}{\widetilde{\mathbf d}}\) \(\newcommand{\evec}{\mathbf e}\) \(\newcommand{\fvec}{\mathbf f}\) \(\newcommand{\nvec}{\mathbf n}\) \(\newcommand{\pvec}{\mathbf p}\) \(\newcommand{\qvec}{\mathbf q}\) \(\newcommand{\svec}{\mathbf s}\) \(\newcommand{\tvec}{\mathbf t}\) \(\newcommand{\uvec}{\mathbf u}\) \(\newcommand{\vvec}{\mathbf v}\) \(\newcommand{\wvec}{\mathbf w}\) \(\newcommand{\xvec}{\mathbf x}\) \(\newcommand{\yvec}{\mathbf y}\) \(\newcommand{\zvec}{\mathbf z}\) \(\newcommand{\rvec}{\mathbf r}\) \(\newcommand{\mvec}{\mathbf m}\) \(\newcommand{\zerovec}{\mathbf 0}\) \(\newcommand{\onevec}{\mathbf 1}\) \(\newcommand{\real}{\mathbb R}\) \(\newcommand{\twovec}[2]{\left[\begin{array}{r}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\ctwovec}[2]{\left[\begin{array}{c}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\threevec}[3]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\cthreevec}[3]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\fourvec}[4]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\cfourvec}[4]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\fivevec}[5]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\cfivevec}[5]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\mattwo}[4]{\left[\begin{array}{rr}#1 \amp #2 \\ #3 \amp #4 \\ \end{array}\right]}\) \(\newcommand{\laspan}[1]{\text{Span}\{#1\}}\) \(\newcommand{\bcal}{\cal B}\) \(\newcommand{\ccal}{\cal C}\) \(\newcommand{\scal}{\cal S}\) \(\newcommand{\wcal}{\cal W}\) \(\newcommand{\ecal}{\cal E}\) \(\newcommand{\coords}[2]{\left\{#1\right\}_{#2}}\) \(\newcommand{\gray}[1]{\color{gray}{#1}}\) \(\newcommand{\lgray}[1]{\color{lightgray}{#1}}\) \(\newcommand{\rank}{\operatorname{rank}}\) \(\newcommand{\row}{\text{Row}}\) \(\newcommand{\col}{\text{Col}}\) \(\renewcommand{\row}{\text{Row}}\) \(\newcommand{\nul}{\text{Nul}}\) \(\newcommand{\var}{\text{Var}}\) \(\newcommand{\corr}{\text{corr}}\) \(\newcommand{\len}[1]{\left|#1\right|}\) \(\newcommand{\bbar}{\overline{\bvec}}\) \(\newcommand{\bhat}{\widehat{\bvec}}\) \(\newcommand{\bperp}{\bvec^\perp}\) \(\newcommand{\xhat}{\widehat{\xvec}}\) \(\newcommand{\vhat}{\widehat{\vvec}}\) \(\newcommand{\uhat}{\widehat{\uvec}}\) \(\newcommand{\what}{\widehat{\wvec}}\) \(\newcommand{\Sighat}{\widehat{\Sigma}}\) \(\newcommand{\lt}{<}\) \(\newcommand{\gt}{>}\) \(\newcommand{\amp}{&}\) \(\definecolor{fillinmathshade}{gray}{0.9}\)This section provides concise definitions of key capital budgeting, project evaluation, and risk analysis terms introduced in Chapter 9. These definitions are presented in a static, printable format for reference and exam preparation. When viewed online, additional dynamic highlighting of terms may be available.
| Term | Definition |
|---|---|
| Abandonment option | A real option that gives management the right (not the obligation) to discontinue a project and recover some value (such as salvage) if results are unfavorable. |
| Base case | The most likely set of assumptions in scenario analysis, used as the benchmark for comparing best- and worst-case outcomes. |
| Break-even analysis (NPV break-even) | An analysis that solves for the value of a key input (such as price or volume) that makes NPV = 0, showing how much “cushion” the project has before value turns negative. |
| Capital budgeting | The process of evaluating and selecting long-term investments by comparing today’s costs to the present value of expected future cash flows. |
| Capital rationing | A situation where a firm has limited funds for investment and must choose among projects, aiming to maximize total NPV within the budget constraint. |
| Crossover rate | The discount rate at which two mutually exclusive projects have the same NPV; found by computing the IRR of the difference in their cash flows (ΔCF). |
| Discount rate (required return) | The rate used to discount future cash flows to present value, reflecting the time value of money and the risk of the project. |
| Discounted payback period | The time required for the cumulative present value of cash inflows to recover the initial investment (incorporates the time value of money). |
| Divisible project | A project that can be scaled up or down (partially funded). Under capital rationing, ranking by PI is most relevant for divisible projects. |
| Equivalent annual annuity (EAA) | A method for comparing projects with unequal lives by converting each project’s NPV into an equivalent constant annual value: \(\text{EAA}=\text{NPV}\times\frac{r}{1-(1+r)^{-n}}\). |
| Hard rationing | Capital constraints imposed externally (for example, lenders or markets restrict financing), creating a binding spending limit even if attractive projects exist. |
| Incremental cash flows | The additional cash inflows and outflows that occur because the project is undertaken; the relevant cash flows for capital budgeting decisions. |
| Indivisible project | A project that must be accepted or rejected in full. Under capital rationing, managers compare feasible combinations to maximize total NPV. |
| Internal rate of return (IRR) | The discount rate that makes a project’s NPV equal to zero. Accept if IRR exceeds the required return, recognizing IRR can mis-rank mutually exclusive projects. |
| Mutually exclusive projects | Projects where accepting one means rejecting the other(s). The correct decision rule is to choose the project with the higher NPV at the required return. |
| Term | Definition |
|---|---|
| Net present value (NPV) | The present value of future cash inflows minus the initial investment. NPV measures total dollar value created; accept if NPV > 0. |
| NPV profile | A graph of NPV versus discount rate. Used to visualize ranking conflicts and identify crossover rates between projects. |
| Payback period | The time required for cumulative nominal cash inflows to recover the initial investment. It is a liquidity screen and ignores the time value of money. |
| Profitability index (PI) | A ratio measuring present value of inflows per dollar invested: \(\text{PI}=\frac{\text{PV(inflows)}}{|\text{CF}_0|}\). Useful for ranking under capital rationing (especially when projects are divisible). |
| Ranking conflict | A situation where different metrics (such as NPV versus IRR or PI) recommend different choices, often due to differences in project scale or cash flow timing. |
| Real option | The right—but not the obligation—to make a future decision about a real asset (such as delaying, expanding, switching, or abandoning a project), representing managerial flexibility. |
| Replacement chain method | A method for unequal lives that repeats the shorter-life project until both alternatives share a common evaluation horizon (often the least common multiple of lives). |
| Scenario analysis | A risk analysis method that changes multiple assumptions together (best/base/worst) to evaluate how combined conditions affect NPV. |
| Sensitivity analysis | A risk analysis method that changes one assumption at a time (holding others constant) to identify which variables have the greatest impact on NPV. |
| Soft rationing | An internally imposed investment budget cap set by management (for planning discipline, risk limits, or leverage targets), even if external financing may be available. |
| Switching option | A real option allowing a firm to change inputs (such as materials or energy source) or outputs (product mix) as conditions change, potentially improving project value. |
| Terminal cash flow | The project’s final period cash flow, which may include salvage value, after-tax proceeds from asset sale, and recovery of net working capital. |
| Tornado chart | A chart (often from spreadsheet sensitivity analysis) that ranks variables by their impact on NPV; longer bars indicate greater influence on value. |
| Timing option (option to delay) | A real option to postpone an investment until uncertainty is reduced (for example, waiting for demand, regulatory clarity, or cost information), potentially increasing value by avoiding premature commitment. |


