  • \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \) \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)\(\newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\) \( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\) \( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\) \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\) \( \newcommand{\Span}{\mathrm{span}}\) \(\newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\) \( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\) \( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\) \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\) \( \newcommand{\Span}{\mathrm{span}}\)\(\newcommand{\AA}{\unicode[.8,0]{x212B}}\)

    Actual and standard quantities and rates for direct labor for the production of 1,000 units are given in the following table. Total actual and standard direct labor costs are calculated by multiplying number of hours by rate, and the results are shown in the last row of the first two columns.

    Direct Labor Cost Variance
     

    Actual

     

    Standard

     

    Difference

    Direct labor quantity in hours

    5,100

     

    5,000

     

    100

    Direct labor rate per hour

    $9.50

     

    $10.00

     

    ($0.50)

    Total direct labor cost

    $48,450

    -

    $50,000

    =

    - $1,550

    The difference column shows that 100 extra hours were used vs. what was expected (unfavorable). It also shows that the actual rate per hour was $0.50 lower than standard cost (favorable). The total actual cost direct labor cost was $1,550 lower than the standard cost, which is a favorable outcome.

    Managers can better address this situation if they have a breakdown of the variances between quantity and rate. Specifically, knowing the amount and direction of the difference for each can help them take targeted measures forimprovement.

    The following table is expanded to include this additional information.

    Screen Shot 2020-06-22 at 2.09.30 PM.png

    The difference in hours is multiplied by the standard price per hour, showing a $1,000 unfavorable direct labor time variance. This is offset by a larger favorable direct labor rate variance of $2,550. The net direct labor cost variance is still $1,550 (favorable), but this additional analysis shows how the time and rate differences contributed to the overall variance.

    The following equations summarize the calculations for direct labor cost variance.

    Direct labor time variance = (actual hours – standard hours) x standard rate

    Direct labor rate variance = (actual rate – standard rate) x actual hours

    Total direct labor cost variance = direct labor time variance + direct labor rate variance


    This page titled 8.3: Direct Labor Cost Variance is shared under a CC BY-SA 4.0 license and was authored, remixed, and/or curated by Christine Jonick (GALILEO Open Learning Materials) via source content that was edited to the style and standards of the LibreTexts platform; a detailed edit history is available upon request.