    \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \) \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)\(\newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\) \( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\) \( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\) \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\) \( \newcommand{\Span}{\mathrm{span}}\) \(\newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\) \( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\) \( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\) \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\) \( \newcommand{\Span}{\mathrm{span}}\)\(\newcommand{\AA}{\unicode[.8,0]{x212B}}\)

    Learning Objectives
    • Understand how manufacturing overhead costs are assigned to jobs.

    Question: We have discussed how to assign direct material and direct labor costs to jobs using a materials requisition form, timesheet, and job cost sheet. The third manufacturing cost—manufacturing overhead—requires a little more work. How do companies assign manufacturing overhead costs, such as factory rent and factory utilities, to individual jobs?

    Answer

    Recall from Chapter 1 that manufacturing overhead consists of all costs related to the production process other than direct materials and direct labor. Because manufacturing overhead costs are difficult to trace to specific jobs, the amount allocated to each job is based on an estimate. The process of creating this estimate requires the calculation of a predetermined rate.

    Using a Predetermined Overhead Rate

    The goal is to allocate manufacturing overhead costs to jobs based on some common activity, such as direct labor hours, machine hours, or direct labor costs. The activity used to allocate manufacturing overhead costs to jobs is called an allocation base7 . Once the allocation base is selected, a predetermined overhead rate can be established. The predetermined overhead rate8 is calculated prior to the year in which it is used in allocating manufacturing overhead costs to jobs.

    Calculating the Predetermined Overhead Rate

    Question: How is the predetermined overhead rate calculated?

    Answer

    We calculate the predetermined overhead rate as follows, using estimates for the coming year: \[\text{Predetermined overhead rate} = \frac{\text{Estimated overhead costs*}}{\text{Estimated activity in allocation base**}}\]

    *The numerator requires an estimate of all overhead costs for the year, such as indirect materials, indirect labor, and other indirect costs associated with the factory. Custom Furniture Company estimates annual overhead costs to be $1,140,000 based on actual overhead costs last year.

    **The denominator requires an estimate of activity in the allocation base for the year. Custom Furniture uses direct labor hours as the allocation base and expects its direct labor workforce to record 38,000 direct labor hours for the year.

    The predetermined overhead rate calculation for Custom Furniture is as follows:

    \[\begin{split} \text{Predetermined overhead rate} &= \frac{$30\; estimated\; overhead\; costs}{38000\; estimated\; direct\; labor\; hours} \\ \\ &= $30\; \text{per direct labor hour} \end{split}\]

    Thus each job will be assigned $30 in overhead costs for every direct labor hour charged to the job. The assignment of overhead costs to jobs based on a predetermined overhead rate is called overhead applied9. Remember that overhead applied does not represent actual overhead costs incurred by the job—nor does it represent direct labor or direct material costs. Instead, overhead applied represents a portion of estimated overhead costs that is assigned to a particular job.

    Question: Now that we know how to calculate the predetermined overhead rate, the next step is to use this rate to apply overhead to jobs. How do companies use the predetermined overhead rate to apply overhead to jobs, and how is this information recorded in the general journal?

    Answer

    As shown on the timesheet in Figure 2.4, Tim Wallace charged six hours to job 50. Because manufacturing overhead is applied at a rate of $30 per direct labor hour, $180 (= $30 × 6 hours) in overhead is applied to job 50. The journal entry to reflect this is as follows:using_predetermined_overhead_rate_a.png

    Recording the application of overhead costs to a job is further illustrated in the T- accounts that follow.

    using_predetermined_overhead_rate_b.png

    When this journal entry is recorded, we also record overhead applied on the appropriate job cost sheet, just as we did with direct materials and direct labor. Figure 2.6 shows the manufacturing overhead applied based on the six hours worked by Tim Wallace. Notice that total manufacturing costs as of May 4 for job 50 are summarized at the bottom of the job cost sheet.
    using_predetermined_overhead_rate_c.png

    Figure 2.6 - Overhead Applied for Custom Furniture Company’s Job 50
    *$180 = $30 per direct labor hour × 6 direct labor hours.

    Selecting an Allocation Base

    Question: Although we used direct labor hours as the allocation base for Custom Furniture Company’s predetermined overhead rate, organizations use various other types of allocation bases. The most common allocation bases are direct labor hours, direct labor costs, and machine hours. What factors do companies consider when deciding on an allocation base?

    Answer

    Companies typically look at the following two items when determining which allocation base to use:

    1. Link to overhead costs. The goal is to find an allocation base that drives overhead costs, often called a cost driver10. For example, if a company’s production process is labor intensive (i.e., it requires a large labor force), overhead costs are likely driven by direct labor hours or direct labor costs. The more direct labor hours worked, the higher the overhead costs incurred. Thus direct labor hours or direct labor costs would be used as the allocation base.

      If a company’s production process is highly mechanized (i.e., it relies on machinery more than on labor), overhead costs are likely driven by machine hours. The more machine hours used, the higher the overhead costs incurred. Thus machine hours would be used as the allocation base.

      It may make more sense to use several allocation bases and several overhead rates to allocate overhead to jobs. This approach, called activity-based costing, is discussed in depth in Chapter 3.
    2. Ease of measurement. An allocation base should not only be linked to overhead costs; it should also be measurable. The three most common allocation bases—direct labor hours, direct labor costs, and machine hours—are relatively easy to measure. Direct labor hours and direct labor costs can be measured by using a timesheet, as discussed earlier, so using either of these as a base for allocating overhead is quite simple. Machine hours can also be easily measured by placing an hour meter on each machine if one does not already exist.

    Why Use a Predetermined Overhead Rate?

    Question: The use of a predetermined overhead rate rather than actual data to apply overhead to jobs is called normal costing11 . Most companies prefer normal costing over assigning actual overhead costs to jobs. Why do most companies prefer to use normal costing?

    Answer

    Companies use normal costing for several reasons:

    • Actual overhead costs can fluctuate from month to month, causing high amounts of overhead to be charged to jobs during high-cost periods. For example, utility costs might be higher during cold winter months and hot summer months than in the fall and spring seasons. Maintenance costs might be higher during slow periods. Normal costing averages these costs out over the course of a year.
    • Actual overhead cost data are typically only available at the end of the month, quarter, or year. Managers prefer to know the cost of a job when it is completed—and in some cases during production—rather than waiting until the end of the period.
    • The price charged to customers is often negotiated based on cost. A predetermined overhead rate is helpful when estimating costs.
    • Bookkeeping is simplified by using a predetermined overhead rate. One rate is used to record overhead costs rather than tabulating actual overhead costs at the end of the reporting period and going back to assign the costs to jobs.

    Using a Manufacturing Overhead Account

    Question: Using a predetermined overhead rate to apply overhead costs to jobs requires the use of a manufacturing overhead account. How is the manufacturing overhead account used to record transactions?

    Answer

    The manufacturing overhead account tracks the following two pieces of information:

    First, the manufacturing overhead account tracks actual overhead costs incurred. Recall that manufacturing overhead costs include all production costs other than direct labor and direct materials. The actual manufacturing overhead costs incurred in a period are recorded as debits in the manufacturing overhead account. For example, assume Custom Furniture Company places $4,200 in indirect materials into production on May 10. The journal entry to reflect this is as follows:

    using_a_manufacturing_overhead_account_a.png

    Other examples of actual manufacturing overhead costs include factory utilities, machine maintenance, and factory supervisor salaries. All these costs are recorded as debits in the manufacturing overhead account when incurred.

    Second, the manufacturing overhead account tracks overhead costs applied to jobs. The overhead costs applied to jobs using a predetermined overhead rate are recorded as credits in the manufacturing overhead account. You saw an example of this earlier when $180 in overhead was applied to job 50 for Custom Furniture Company. We repeat the entry here.

    using_a_manufacturing_overhead_account_b.png

    The following T-account summarizes how overhead costs flow through the manufacturing overhead account:

    using_a_manufacturing_overhead_account_c.png

    The manufacturing overhead account is classified as a clearing account12 . A clearing account is used to hold financial data temporarily and is closed out at the end of the period before preparing financial statements.

    Underapplied and Overapplied Overhead

    Question: Because manufacturing overhead costs are applied to jobs based on an estimated predetermined overhead rate, overhead applied (credit side of manufacturing overhead) rarely equals actual overhead costs incurred (debit side of manufacturing overhead). What terms are used to describe the difference between actual overhead costs incurred during a period and overhead applied during a period?

    Answer

    Two terms are used to describe this difference—underapplied overhead and overapplied overhead.

    Underapplied overhead13 occurs when actual overhead costs (debits) are higher than overhead applied to jobs (credits). The T-account that follows provides an example of underapplied overhead. Note that the manufacturing overhead account has a debit balance when overhead is underapplied because fewer costs were applied to jobs than were actually incurred.

    underapplied_and_overapplied_overhead_a.png

    Overapplied overhead14 occurs when actual overhead costs (debits) are lower than overhead applied to jobs (credits). The T-account that follows provides an example of overapplied overhead. Note that the manufacturing overhead account has a credit balance when overhead is overapplied because more costs were applied to jobs than were actually incurred.
    Table 2: Manufactoring Overheard
    debit credit
    actual overheard Overhead cost
    cost incurred applied to jobs
    $6,000 $9,000
      $3,000 (balance)
    underapplied_and_overapplied_overhead_b.png
    Business in Action 2.1

    Job Costing at Boeing

    Boeing Company is the world’s leading aerospace company and the largest manufacturer of commercial jetliners and military aircraft combined. Boeing provides products and services to customers in 150 countries and employs 165,000 people throughout the world.

    buisiness_in_action_2_1.png

    Source: Photo courtesy of prayitno, http://www.flickr.com/photos/34128007@N04/5293183651/.

    Since most of Boeing’s products are unique and costly, the company likely uses job costing to track costs associated with each product it manufactures. For example, the costly direct materials that go into each jetliner produced are tracked using a job cost sheet. Direct labor and manufacturing overhead costs (think huge production facilities!) are also assigned to each jetliner. This careful tracking of production costs for each jetliner provides management with important cost information that is used to assess production efficiency and profitability. Management can answer questions, such as “How much did direct materials cost?,” “How much overhead was allocated to each jetliner?,” or “What was the total production cost for each jetliner?” This is important information when it comes time to negotiate the sales price of a jetliner with a potential buyer like United Airlines or Southwest Airlines.

    Source: Boeing, “Home Page,” http://www.boeing.com.

    Closing the Manufacturing Overhead Account

    Question: Since the manufacturing overhead account is a clearing account, it must be closed at the end of the period. How do we close the manufacturing overhead account?

    Answer

    Most companies simply close the manufacturing overhead account balance to the cost of goods sold account. For example, if there is a $2,000 debit balance in manufacturing overhead at the end of the period, the journal entry to close the underapplied overhead is as follows:

    closing_the_manufacturing_overhead_account_a.png

    If manufacturing overhead has a $3,000 credit balance at the end of the period, the journal entry to close the overapplied overhead is as follows:
    closing_the_manufacturing_overhead_account_b.png

    Alternative Approach to Closing the Manufacturing Overhead Account

    Question: Although most companies close the manufacturing overhead account to cost of goods sold, this is typically only done when the amount is immaterial (immaterial is a common accounting term used to describe an amount that is small relative to a company’s size). The term material describes a relatively large amount. How do we close the manufacturing overhead account when the amount is material?

    Answer

    If the amount is material, it should be closed to three different accounts—work-in-process (WIP) inventory, finished goods inventory, and cost of goods sold—in proportion to the account balances in these accounts.

    For example, suppose a company has $2,000 in underapplied overhead (debit balance in manufacturing overhead) and that the three account balances are as follows:
    alternative_approach_to_closing_a.png

    The $2,000 is closed to each of the three accounts based on their respective percentages. Thus $1,200 is apportioned to WIP inventory (= $2,000 × 60 percent), $600 goes to finished goods inventory (= $2,000 × 30 percent), and $200 goes to cost of goods sold (= $2,000 × 10 percent). The journal entry to close the $2,000 underapplied overhead debit balance in manufacturing overhead is as follows:

    alternative_approach_to_closing_b.png

    Although this approach is not as common as simply closing the manufacturing overhead account balance to cost of goods sold, companies do this when the amount is relatively significant.

    Key TakeawayS
    1. Most companies use a normal costing system to track product costs. Normal costing tracks actual direct material costs and actual direct labor costs for each job and charges manufacturing overhead to jobs using a predetermined overhead rate. The predetermined overhead rate is calculated as follows: $$\text{Predetermined overhead rate} = \frac{\text{Estimated overhead costs}}{\text{Estimated activity in allocation base}}$$
    2. A manufacturing overhead account is used to track actual overhead costs (debits) and applied overhead (credits). This account is typically closed to cost of goods sold at the end of the period.
    review problem 2.3
    1. Chan Company estimates that annual manufacturing overhead costs will be $500,000. Chan allocates overhead to jobs based on machine hours, and it expects that 100,000 machine hours will be required for the year. Calculate the predetermined overhead rate.
    2. Why might Chan Company use machine hours as the overhead allocation base?
    3. Chan Company received a bill totaling $3,700 for machine parts used in maintaining factory equipment. The bill will be paid next month. Make the journal entry to record this transaction.
    4. Job 153 used a total of 2,000 machine hours. Make the journal entry to record manufacturing overhead applied to job 153. What other document will include this amount?
    5. Job 153 used a total of 2,000 machine hours. Make the journal entry to record manufacturing overhead applied to job 153. What other document will include this amount?
      1. Is overhead overapplied or underapplied? Explain your answer.
      2. Make the journal entry to close the manufacturing overhead account assuming the balance is immaterial.
      3. Make the journal entry to close the manufacturing overhead account assuming the balance is material.
    Answer
    1. The predetermined overhead rate is calculated as follows: $$\begin{split} \text{Predetermined overhead rate} &= \frac{\text{Estimated overhead costs}}{\text{Estimated activity in allocation base}} \\ \\ &= \frac{$500000\; estimated\; overhead\; cost}{100000\; machine\; hours} \\ \\ &= $5\; per\; machine\; hour \end{split}$$
    2. If Chan’s production process is highly mechanized, overhead costs are likely driven by machine use. The more machine hours used, the higher the overhead costs incurred. Thus there is a link between machine hours and overhead costs, and using machine hours as an allocation base is preferable.

      Machine hours are also easily tracked, making implementation relatively simple.

    3. 2_3_anr3.png
    4. A total of $10,000 (= $5 per machine hour rate × 2,000 machine hours) will be applied to job 153 and recorded in the journal as follows:2_3_anrs4.png​​​​​​
      This amount will also be recorded on the job cost sheet for Job 153.
      1. Overhead is overapplied because actual overhead costs are lower than overhead applied to jobs. Also, the manufacturing overhead account has a credit balance.

      2. 2_3_anrs5_2.png
      3. 2_3_anrs5_3_a.png
        *Amounts are calculated as follows. Allocation amount = percent of total × the overapplied balance of $40,000.
        2_3_anrs5_3_b.png

    Definitions

    1. The activity used to allocate manufacturing overhead costs to jobs.
    2. A rate established prior to the year in which it is used in allocating manufacturing overhead costs to jobs.
    3. The assignment of overhead costs to jobs based on a predetermined overhead rate.
    4. The allocation base that drives overhead costs.
    5. A method of costing that uses a predetermined overhead rate to apply overhead to jobs.
    6. An account used to hold financial data temporarily until it is closed out at the end of the period.
    7. Overhead costs applied to jobs that are less than actual overhead costs.
    8. Overhead costs applied to jobs that exceed actual overhead costs.

    This page titled 2.4: Assigning Manufacturing Overhead Costs to Jobs is shared under a CC BY-NC-SA 3.0 license and was authored, remixed, and/or curated by Anonymous via source content that was edited to the style and standards of the LibreTexts platform; a detailed edit history is available upon request.